Thursday, December 12, 2013

Progress Update: Week of Dec. 2nd

This post is a week late but it highlights all that was completed last week. The group met last Friday to put the project together and test out how the 3D printed parts would work. We ran into a problem however when we realized we were missing a very important part since it wasn't with our other printed pieces. This piece was the wheel that would be attached to the main servo motor and the 3D printed Lego piece. Without it, we were able to connect all the other parts and see how they would function but couldn't put the entire project together. However we did accomplish many things while working on the project that day:

  • Putting 3D printed parts together
  • soldering wires to push buttons and LEDs
  • Building a base and frame for the entire project out of Legos
Here are two pictures of what the project looked like so far,

No comments:

Post a Comment